Perth and Kinross council – A93 Rochallie land slip
Duration – 16 weeks
July 2015
The works involved putting new drainage measures and kerbing measures into control the flow of carriageway drainage and surfacing over 500m of carriageway.
Installation of gabion wall at the existing land slip, gabion rhino mattress to create a valley of drainage down the slope to control flow of road drainage. All gabions were soil nailed and anchored to the embankment.