  • Kenmore Landslip

    Perth and Kinross – Kenmore landslip

    Duration – 16 weeks

    June 2014

    Kenmore landslip was a partial collapse of the carriageway built on top of a 16m high embankment, the works involved cutting, benching, installation of 10000 tons of structural fill and regrading to new the existing slope.
    Carriageway drainage and surfacing works.
    500m cubed of gabion wall works and gabion cascade all installed by our own staff.